Remember,
Duration x Units = Work
Fixed Duration suggested that the task the task must be completed within a given duration. As you assign a single or multiple resources to the task, Microsoft Project will automatically calculate the appropriate resource allocation percentage to ensure the task is completed within the given duration.
Fixed Work suggests that a task has a specific numbers of hours work associated with it. In this scenario, we know that the task is going to take ten hours to complete. We have the ability to schedule the tasks overall duration for five days with fixed work of ten hours. Assuming a single resource is responsible for completing the task, Microsoft Project will schedule the resource to work two hours a day for the five day duration.